Insulating the frame...

The timber frame to the main building is now mostly complete, and we've started to install the recycled paper (cellulose) insulation, between the internal OSB board sheathing and the external woodfibre sheathing boards.

This is done by simply blowing the insulation into the frame, with a large reverse hoover - and making sure you stop the machine before it's full so you don't get covered in fluffy insulation!

Meanwhile, the internal works are proceeding with 'first fix' mechanical and electrical installs. 

 

 

Image: 
the 'blowing machine'